Describes the post-construction HVAC system commissioning process done at a new historical museum and archival storage facility. Improper functioning of HVAC was discovered. The building was commissioned after occupation. The paper describes the process of rectifying the problems, and emphasises the importance of employing a commissioning agent throughout the design and construction process.
Commissioning a museum and archival storage facility.
Bibliographic info:
USA, Atlanta, ASHRAE (American Society of Heating, Refrigerating and Air Conditioning Engineers), Transactions: Symposia, pp 476-481, 1 tab.