Dickinson J.B. Grimsrud D.T. Krinkel D.L. Lipschutz R.D.
Year:
1982
Bibliographic info:
LBL Report no.12742 February 1982 75pp. 9 tabs. 6 figs. 17 refs. #DATE 01:03:1982 in English

Describes a project carried out by the Bonneville Power Administration where 18 houses at its Midway substation in central Washington were retrofitted and the results monitored for a 3 year period. The houses were divided into 3 groups. During